Construction Schedule
2007 Dates
Summer 2007
West Hall Flagpole Relocation - completed
Pound Hall Computer Classroom - in progress
Fine Arts Gallery Renovation - in progress
Pound Hall Faculty Offices - in progress
Ropes Course - in progress
New Chiller Plant - in progress
Education Center Faculty Office - in progress
University Center Renovation of Theater, Magnolia Room, and Executive Dining Room - begining
Demolition of Hopper Hall-
Beginning
Student Union - in design
Demolition of Union & Gym -
Beginning
Fall 2007
Pound Hall Computer Classroom - completed
Fine Arts Gallery Renovation - completed
Pound Hall Faculty Offices -completed
Ropes Course - completed
New Chiller Plant - completed
Education Center Faculty Office - completed
University Center Renovation of Theater, Magnolia Room, and Executive Dining Room - completed
New Hopper Hall Construction- begining
Nevins Hall Renovation - in design
Student Union - in design
2008 Dates
Spring 2008
New Hopper Hall Construction - in progress
Nevins Hall Renovation -
beginning
Sustella Parking deck-
beginning
Student Union - in design
Oak Street Parking deck-
beginning
Summer 2008
New Hopper Hall Construction - in progress
Nevins Hall Renovation - in progress
Sustella Parking deck- in progress
Student Union Construction - beginning
Oak Street Parking deck- in progress beginning
Fall 2008
New Hopper Hall - completed
New Georgia Hall - beginning
Reade Hall renovations - beginning
Nevins Hall Renovation - in progress
Sustella Parking deck- completed
Oak Street Parking deck- completed
Student Union - in progress
Georgia Hall Demolition- completed
2009 Dates
Spring 2009
New Georgia Hall - in progress
Reade Hall renovations - completed
Student Union - completed
Summer 2009
New Georgia Hall - completed